李义宾.莱歇立磨现场安装中两个工序的实践[J].水泥工程,2018,31(3):46-49
莱歇立磨现场安装中两个工序的实践
Practice of two processes in the field installation of Loesche vertical mill
  
DOI:
中文关键词: 莱歇立磨  现场安装  工序  基础框架  焊接  立柱
英文关键词: Loesche vertical mill  field installation  process  foundation frame  welding  column
基金项目:
作者单位
李义宾 中建材国际装备有限公司 
摘要点击次数: 1354
全文下载次数: 0
中文摘要:
      在立磨的现场安装中,基础框架的组装及焊接、立柱与连接桥及立柱与基础框架的组装及焊接这两个工序是整个安装装施工过程中的关键工序之一。通过在莱歇立磨LM56.3+3CS现场安装过程中的实践,详细总结了莱歇立磨这两个工序的施工过程,在施工过程中,还及时进行了多次检测,使得施工质量及效率得到了保障。
英文摘要:
      In the field installation of vertical mill, there are two key processes in the whole intallation——the assembly and welding of the basic frame, the assembly and welding of the column and the connecting bridge, the column and the foundation frame. By the field installation practice of LM56.3+3CS, the construction process of the two processes is summarized in detail. In the process of construction, many tests have been carried out in time, so the quality and efficiency of the construction are guaranteed.