孙朝飞,周 巍,陈 晨,夏 芸.池州矿产品运输廊道线路规划设计方案比选[J].水泥工程,2024,37(2):86-88 |
池州矿产品运输廊道线路规划设计方案比选 |
Comparison and selection of planning and design schemes for the transportation corridor of Chizhou mineral products |
|
DOI: |
中文关键词: 运输廊道,设计方案,比选 |
英文关键词: transportation corridor, design scheme,comparison and selection |
基金项目: |
|
摘要点击次数: 142 |
全文下载次数: 0 |
中文摘要: |
池州中建材新材料暨港廊一体化项目矿产品运输廊道线路总长约36 km,其中隧道段约13 km,高架段约23 km,设计年运输能力6000万t。线路规划选择过程中涉及土地规划、基本农田、生态红线、公益林等条件限制,设计实施过程中涉及输电线路、通讯线路、铁路、各等级道路、各种管线的设计难点。 |
英文摘要: |
Chizhou mineral products transportation gallery project overland belt conveyor length is about 36 km, including about 13 km tunnel section, about 23 km steel truss section, design annual transportation capacity is 60 million tons. The route selection restriction involves land planning, basic farmland, ecological red line, public welfare forest and other conditions. The design implementation involves the design difficulties of riverway, electricity transmission lines, communication lines, railways, roads, and various pipelines. |
查看全文
查看/发表评论 下载PDF阅读器 |
关闭 |
|
|
|